Dependency check (cycles, missing tasks), forward pass ES/EF, backward pass LS/LF, float per task, all paths listed with their length. Then crashing: cheapest cut per day, every path re-measured after each cut, until the deadline is met or proven impossible…
About this prompt
Turns a task list with durations and dependencies into a critical path schedule: forward and backward pass, earliest and latest dates, float for every task. If the deadline is too tight, it works out the cheapest combination of tasks to speed up (crashing), one day at a time, re-checking every path after each cut. DeepSeek is used because the method is pure step-by-step calculation that you need to be able to audit.
Example output
FORWARD AND BACKWARD PASS
| Task | Dur | Pred | ES | EF | LS | LF | Float |
| A | 3 | — | 0 | 3 | 0 | 3 | 0 |
| B | 5 | A | 3 | 8 | 4 | 9 | 1 |
| C | 2 | A | 3 | 5 | 3 | 5 | 0 |
| D | 4 | C | 5 | 9 | 5 | 9 | 0 |
| E | 3 | B, D | max(8, 9) = 9 | 12 | 9 | 12 | 0 |
PATHS: A-B-E = 3 + 5 + 3 = 11; A-C-D-E = 3 + 2 + 4 + 3 = 12 (critical). Deadline 10 → 2 days to recover.
CRASHING (cost per day: A 600, B 250, C 300, D 200, E 500)
Day 1: only A-C-D-E is critical. Cheapest task on it: D (200). D 4 → 3. Paths: A-B-E 11, A-C-D-E 11.
Day 2: both paths critical. Options: A (600), E (500), D + B (200 + 250 = 450), C + B (300 + 250 = 550). Choose D + B: D 3 → 2, B 5 → 4.
Paths: A-B-E = 3 + 4 + 3 = 10 ✓; A-C-D-E = 3 + 2 + 2 + 3 = 10 ✓
| Cut | Tasks | Cost | Cumulative |
| 12 → 11 | D | 200 | 200 |
| 11 → 10 | D + B | 450 | 650 |
Deadline met for 650. Every task now has zero float: any slip moves the end date…
Details
- Model
- DeepSeek
- Prompt language
- English
- Who it's for
- Project managers, event planners, contractors and team leads with a fixed deadline
- Length
- ~569 tokens (estimate)
- Delivered as
- Prompt text, shown online after purchase
- Category
- Productivity
Reviews
No reviews yet. Only buyers of this prompt can leave one.